Below is a list of our open audit recommendations. When a report is issued, the Postal Service responds to each recommendation, and if there is agreement, it provides a corrective action plan with a date of planned implementation. We request written confirmation from the Postal Service when those corrective actions are completed and evaluate this information and provide concurrence when the recommendation can be closed.
If the Postal Service disagrees with a recommendation, we work towards agreement by elevating discussions between USPS and OIG management. Any recommendations that the Postal Service does not act on remain open and are reported to Congress until a resolution is achieved.
Create a comprehensive plan to manage legacy systems to include defining legacy systems according to best practices, identifying all legacy systems, and developing a plan of action and milestones to enforce timely mitigation of identified risks related to legacy systems.
$0
Closed
Disagree
Agree
2
Mitigate identified risks for all legacy systems, develop a plan of action and milestones to enforce timely mitigation of identified risks related to legacy systems and report the status of mitigations as defined in the Corporate Information Security Office's plan of action and milestones to the Corporate Information Security Office.
Continue to document the issues identified and actions taken to address issues in post implementation reviews of Regional Processing and Distribution Center (RP&DC) conversions, and use the cumulative lessons learned when activating future RP&DCs.
$0
Closed
Agree
2
Develop procedures to identify and mitigate challenges at facilities scheduled to become a Regional Processing and Distribution Center before launch.
$0
Closed
Agree
3
Coordinate the training of Richmond Regional Processing and Distribution Center (RP&DC) management on how to engage and lead team members and provide adequate supervision of operations, and deploy management training at future RP&DC sites prior to launch.
$5,021,051
Closed
Agree
4
Develop a scorecard to track service performance and include it as a measure of success at both the Richmond Regional Processing and Distribution Center (RP&DC) and when implementing future RP&DCs.
$0
Closed
Agree
5
Align transportation schedules to operations and validate with local management before launching Regional Processing and Distribution Centers.
$2,948,034
Closed
Agree
6
Direct personnel to record omitted trips in the data systems and pursue recovery of payments for cancelled trips at the Richmond Regional Processing and Distribution Center.
$115,690
Closed
Agree
7
Train all management personnel in the Richmond region to understand and perform their roles and responsibilities as stated in the Richmond Regional Processing and Distribution Center integrated operating plan.
$0
Closed
Agree
8
Implement a process to communicate with and solicit feedback from affected managers when developing plans for and implementing future Regional Processing and Distribution Centers.
$0
Closed
Agree
9
Update Handbook PO-408 to include the definition of service area, and clearly define when Mail Processing Facility Reviews are required.
$0
Open
Agree
10
Communicate any impacts to customers when permanently moving processing operations of a three-digit ZIP Code to another processing facility.
Finalize the method for tracking contractor accident and fatality data and establish corresponding written policies and procedures, including related roles and responsibilities.
$0
Closed
Agree
2
Require freight auction brokers to report subcontractor authorization and vetting and develop a system of record to maintain the reported results.
$0
Closed
Disagree
Agree
3
Clarify, communicate, and enforce subcontractor authorization guidance for highway contract route contractors and terminate contractors who are non-compliant.
$0
Closed
Agree
4
Develop requirements and implement a mechanism to track highway contract route contractors and the subcontractors they utilize.
$0
Closed
Disagree
Disagree
5
Communicate and create a mechanism to validate the use of team drivers for trips that exceed 500 miles, update freight auction statements of work, and terminate contractors who are non-compliant.
$0
Closed
Disagree
Agree
6
Define freight auction applicability to Management Instruction PO-530-2009-4, Section 19 " Special Circumstances.
$0
Open
Disagree
Disagree
7
Update and enforce freight auction guidance and include at minimum a process to verify driver history.
Develop a plan to include proposed quantities, projected cost, and actionable milestones to fully deploy the eArrow lock and high security mailbox initiatives, and include measures to assess their effectiveness.
$0
Open
Disagree
Agree
2
Provide new and acting managers and supervisors training on arrow key policies upon assuming their roles and maintain documentation of training attendance.
$0
Closed
Agree
3
Develop an oversight mechanism to hold managers and supervisors accountable for following established arrow key policy and training requirements.
$0
Closed
Agree
4
Finalize the Mail Theft Strategy that is under development by the end of calendar year 2023.
$0
Closed
Agree
5
Assess staffing resources available nationwide to support the Mail Theft Program and align resources with their Mail Theft Strategy.
$0
Closed
Agree
6
Require postal inspectors to complete the In-Service Basic Mail Theft training within one year of being assigned to a mail theft team.
$0
Closed
Agree
7
Work with the contracting officer to modify the existing contract and 1) define the Mail Theft Analytics Program purpose to improve complaint data quality and usefulness for division personnel, 2) develop internal controls such as guidance and an oversight mechanism, and 3) establish performance metrics to assess the effectiveness of the program.
Develop a plan to analyze costs associated with the processing and delivery of Election Mail and explore opportunities to be compensated for the implementation of Election Mail key practices and extraordinary measures.
$23,033,770
Open
Disagree
2
Evaluate if all current Election Mail policies are necessary and eliminate redundancies.